DUMFRIES - Scotgen (Dumfries) Ltd – Dargavel Energy from Waste Facility, PPC Permit: PPC/A/1022412

(Return to 'Existing Waste Burners')

Site Status Reports

Quarterly reports

Sampling results

Incident Reports, March - September 2010

Annual Reports - 2009

--------------------------

Update, 3 November 2010

Update, 13 September 2010 - Click here to see the full 'Site Status Report' for September 2010

Since commissioning re-started in March 2010 (data correct to 05 September 2010) there have been 17 recorded noise complaints, 15 activations of the by-pass stack, 2 failures of the Continuous Emission Monitoring System and 172 notifications of short term ELV breaches: 10 VOC / 22 CO / 65 low temp at Secondary Combustion Chamber exit / 66 low O2 / 2 NO2 / 2 SO2 / 1 HCl / 4 dust.

Most of these breaches last a few minutes until the process control systems correct to bring emissions back within range. Such breaches are not unexpected during commissioning as the Operator adjusts the system.  

Records for each incident are available for inspection on our Public Register (at East Kilbride). The contact details can be found via this link. 

--------------------------

Update, 2 July 2010 - here is an excerpt (click here to see full document provided by SEPA)

This Installation was Permitted in May 2009 and began commissioning in October that year. There followed an extended outage between December 2009 and March 2010. The plant is still under the commissioning phase. Since commissioning recommenced in March 2010 (till the end of May 2010) there have been 22 breaches of the Secondary Combustion Chamber oxygen limit, 13 breaches of the Secondary Combustion Chamber temperature limit, 3 activations of the by-pass stack, 1 breach of the VOC emission limit, 2 breaches of the CO emission limit and 6 noise complaints.

--------------------------

Update on emission breaches, 8 June 2010

No breaches of Emission Limit Values are recorded for Quarter 1 2010. The permit for this installation was granted in May 2009. The installation has not yet started full operation (commissioning phases started in October 2009 and are ongoing after an extended plant outage between December 2009 and March 2010). Other incidents / non compliances not relevant to emission limit values are not included. The Operator has reported a number of breaches of the nominal multi tier emission limit values. However; in most cases, compliance with these emission limit values (that are based on a percentage compliance requirement over a calendar year) cannot
be established until January 2011. The emission limits require either 100% compliance with a single 30 minute average value or a percentage compliance requirement over a year long time period. The permit was varied in May 2010 to clarify further the time basis over which compliance is to be established for emission limit values expressed on a percentage basis.

--------------------------

Emission Limit breaches in 2009 - PDF file

Related news stories

Perth Council ignores SITA's misleading statement to Development Control Committee, 4 December 2011
Chief Executive of Perth and Kinross Council refuses to take action over misleading statements by SITA UK over its application to build a waste gasification incinerator at Binn Farm near Abernethy...read more

 

Binn Farm, Perth - Claims council were misled over plans for incinerator, 26 Nov 2011
A LEADING environmental campaigner has claimed that Perth and Kinross Council was "misled" over plans for Binn Farm. Michael Gallagher, secretary for Green Alternatives...read more

 

Irresponsible view? Dovesdale court case begins, 27 Oct 2011
THE Judicial Review into the Dovesdale Incinerator has started at the Court of Session in Edinburgh. On Friday members from Dovesdale Incinerator Action Group...read more

 

Row as South Lanarkshire Council’s award £459m waste contract, Sep 8 2011
SOUTH Lanarkshire’s municipal waste will NOT be disposed of at the controversial incinerator planned for Dovesdale Farm, between Larkhall and Stonehouse...read more

Perth could be new Bhopal - stack claim - 24 June 2011
COMMUNITY councillors battling Grundon's controversial new incinerator plans warn they could spell disaster for Perth, writes Gordon Bannerman...read more

Isle of Wight seeks to reduce use of 'unreliable' gasifier, 22 June 2011
The Isle of Wight council has outlined plans to radically overhaul its waste and recycling service in a bid to reduce its dependence on the “unreliable” gasification...read more

Dargavel update from SEPA, 30 March 2011

From March 2010 until March 2011 there have been 37 activations of the bypass stack. In the main these activations were...read more

Visit to Dumfries gasifier reveals dirty truth, 9 February 2011

Dargavel gasification plant was even worse than we'd feared...read more

Derby victory in Sinfin appeal, 16 Nov

Campaigners in Derby are celebrating the failure of Resource Recovery Solutions (Derbyshire) Limited to overturn on appeal the decision of Derby City Council....Read more

Dumfries gasifier has still to create any energy, 8 Oct

A £20 MILLION renewable energy plant is failing to produce any power – more than a year after it was opened. The Scotgen “energy from waste” plant is meant...read more

Waste incinerator company in emission safety breaches, 28 July

Campaigners with Dovesdale Action Group are fighting plans for a £50m waste disposal unit A company that wants to build a controversial waste disposal...read more

"Strip gasifier of ROCs", demand Derby FOE - 16 July

Derby Friends of the Earth have called on electricity regulator OFGEM to withdraw preliminary accreditation of ROCs for the Isle of Wight gasification plant for the following breaches of RO Generator Guidance...read more